Boviet Solar Cell Manufacturing Facility

Greenville, NC

Boviet Solar needed a facility where they could manufacture cells that are installed in solar panels. This project highlights Scout & Co’s dedication to flexibility, ensuring that clients’ needs are met and deadlines are exceeded when possible.

Challenge

The project site’s existing flat terrain would require a large volume of imported fill to achieve the original design grades. This had the potential to increase project costs, as well as add time to the overall project timeline.

Solution

The team created multiple iterations of the site and stormwater infrastructure design to ensure the site elevation could be lowered and still be functional, with as little cost impact as possible.

Results

We offered expedited design that allowed design duration to shrink from 1.5 months to just 3 weeks, allowing for initial permit submission to be into the City 3 weeks sooner than expected.